Skip Navigation
*To search for student contact information, login to FlashLine and choose the "Directory" icon in the FlashLine masthead (blue bar).

Description of Current Projects

Pardon Our Dust! Allerton Apartments Abatement and Demolition, Phase 2: Units A, B, C and D
Design and bid documents are being prepared by The Osborn Engineering Company for the abatement and demolition of the remaining Allerton Apartment Units A, B, C and D. Corresponding studies are being produced to show this green space being utilized as athletic fields. This project is anticipated to be advertised for bidding in late 2014. Demolition will begin late summer 2015 after leases expire. This General Contracting project is being managed via OAKS-CI.

Beall, McDowell, Prentice, and Dunbar Halls HVAC Replacement and Student Room Improvements
The three buildings within the Twin Towers Complex, Beall and McDowell halls, and Twin Towers Center, were all constructed in 1966; both Prentice and Dunbar halls were built in 1959. Over the past ten years, Residence Services has invested funds to address critical safety needs such as fire alarm, fire door, power systems and room security improvements, as well as invested in major shower and toilet room improvements, elevator replacements and accessibility enhancements. With this project, Residence Services will replace the HVAC systems and make student room improvements in Beall, McDowell, Prentice, and Dunbar halls. The project will include the demolition of the existing two-pipe convection heating units and installation of new, four-pipe heating and air conditioning fan coil units along with the associated piping, power and temperature control infrastructure in Beall, McDowell, and Prentice halls; Dunbar Hall is planned to remain a two-pipe heating-only system. All heating, ventilation and air conditioning systems will be designed to meet the university’s energy and sustainability goals. The existing asbestos-containing floor tile within the residence rooms and corridors will be replaced with carpet tile floor finishes. While Beall and McDowell halls' existing student room built-in wardrobe units will be demolished, the contractor will be responsible for managing the temporary removal and storage of the remaining student room furniture in all four buildings. The contractor will return the furniture and coordinate with the university’s furniture vendor for installation of the new wardrobe units. Van Auken Akins Architects, LLC is serving as the Criteria Architect/Engineer and Gilbane Building Company is serving as the Design-Builder for this project. Construction work within tunnels and mechanical areas is anticipated to begin in late 2014, and the main construction work within the buildings will commence and be completed during the summer of 2015. This Design-Build project is being managed via OAKS-CI.

Bowman Hall Fire Alarm Replacement Bowman Hall's existing fire alarm system, original to the three-story with partial basement, 84,500 SF building, has failed and replacement parts are no longer available. The system was expanded upon in a renovation with a newer panel, but that panel is too small to support the whole building. This project removes the existing fire alarm system and replaces it with a new, addressable, voice evacuation system. The electrical contract award is pending with the Apparent Low Bidder, M & M Electrical Contractors for construction bids that were opened on September 19 for this project that was designed by Thorson Baker + Associates, Inc.. This General Contracting project is being managed via OAKS-CI.

Centennial Court ADA Improvements
This project, designed by Metropolitan Architecture Studio, details necessary ADA enhancements, including revisions to restroom layouts, in the Centennial Court residence halls. Field investigation work was completed over the summer of 2014. Bidding is anticipated for early 2015 with construction commencing during the summer of 2015. This General Contracting project is being managed via OAKS-CI.

College of Podiatric Medicine Parking Lot Rehabilitation
The existing parking lot at the College of Podiatric Medicine are being rehabilitated. The current parking lot surface course is beyond its intended life span and is in need of repair/replacement; curbs are damaged and some have been paved up to the top. Work includes investigation into subsurface condition and existing layers of asphalt. EnviroCom Construction's work commenced on August 25 and continues until December 23 for this project that was designed by Karpinski Engineering, Inc. This General Contracting project is being managed via OAKS-CI.

East Campus Chilled Water Plant New Chiller and New Chiller Plate and Frame
This project, designed by Scheeser Buckley Mayfield, adds a new chiller and cooling tower to the existing East Campus Chilled Water Plant facility. As more residence halls have been upgraded to have air conditioning, the demands on the existing infrastructure have increased. This new equipment allows for system growth and redundancy while providing energy savings and peak performance. Design work is underway and the project is anticipated to be advertised for bidding during October. Construction will proceed in phases so as to not interrupt any chilled water service to the residence halls. This General Contracting project is being managed via OAKS-CI.

Engleman Hall ADA Improvements
This project, designed by Metropolitan Architecture Studio, details necessary ADA enhancements, including revisions to restroom layouts, in Engleman Hall. Field investigation work was completed over the summer of 2014. Bidding is anticipated for early 2015 with construction commencing during the summer of 2015. This General Contracting project is being managed via OAKS-CI.

Geauga Classroom Building HVAC Replacements, Multiple Phases
In 2010, Kent State University at Geauga commissioned a study to evaluate the Classroom Building's heating, ventilation and air conditioning systems to determine and recommend which HVAC equipment and systems are most in need of replacement and to recommend a system type for replacement. Karpinski Engineering, Inc. designed the multiple phases of this project. Future phases will complete the HVAC replacements over several projects during the course of several years. Pending the approval and release of state funding, design of the final Phase 4 should commence in the fall. Phase 4 work is anticipated to be bid by the end of the year in order for construction to commence during the spring of 2015. This General Contracting project is being managed via OAKS-CI.

Kent Campus Classroom, Laboratory, Auxiliary Buildings and Utility Assets Energy Conservation Project, Phase I
In mid-November 2012, The Brewer-Garrett Company commenced activity on their Performance Contract services for energy conservation measures in Kent Campus classroom, laboratory and auxiliary buildings, Summit Street Power Plant and utilities infrastructure. This project impacts over 3.6 million square feet of buildings, plus parking lot and roadway lighting and campus utilities (electricity, natural gas, chilled water, steam, domestic water and sewer). The potential fifty million dollar project was limited to a twenty-five million dollar Phase 1 with a possible, but yet to-be-determined value, future Phase 2. External special bond funding was approved by the Kent State University Board of Trustees and the Ohio Air Quality Development Authority; funding all-in rate achieved 1.25% with a very positive effect on project cash flow. The project is utilizing Ohio House Bill 7 Performance Contracting regulations for payback of the project costs with guaranteed energy savings and possibly operational and avoided capital costs over a maximum 15-year time period. Expectation for Phase 1 of this project is that the majority of the House Bill 251 energy use reduction goal of 20% will be met. A substantial amount of noticeable Phase 1 work is complete with final construction and installation of items continuing through the end of October. New windows were installed at: Administrative Services Building, Bowman Hall, DeWeese Health Center, Dix Stadium, and the Kent State University Museum at Rockwell Hall. New HVAC equipment was installed at: MAC Center, Schwartz Center, and the Ice Arena. The majority of the campus exterior pole lighting project retrofitting to LED is complete. The Power Plant’s gas and electric utility contract/operation re-negotiation is also included in Phase 1 (electric contracts complete for all campuses). Select envelope deferred renewal projects are complete at: Administrative Services Building, Bowman Hall, DeWeese Health Center, Dix Stadium, KSU Museum, and Nixson Hall (skylights). Bowman, Henderson, Moulton, and Nixson halls received new roofs. Additional envelope restorations are currently being conducted on Henderson Hall. Between May and August, new windows were installed and envelope repairs were completed at the Library. General project scope items include select lighting retrofits to about seventy-seven buildings/structures (complete), replacements of air handlers (MAC Center Gym complete), chillers, boilers, pumps, heat exchangers and domestic water heating systems (Schwartz Center complete), installation of piping system insulation, building envelope repairs, and comprehensive utility metering. Six groups of contractor teams retrofitted interior lighting at many buildings. A Web-based energy usage dashboard will be developed in late 2014. During the summer, specialty lighting retrofits occurred in many buildings, along with occupancy sensor and other lighting controls installation in about seventy-seven buildings/areas. Project completion is on target for the end of October 2014.

Korb Hall Elevator Modernization
This project, designed by Van Auken Akins Architects, details the modernization of Korb Hall’s elevator. This project will utilize the existing hoistway while making improvements to the elevator machinery and adding necessary fire prevention features. Design work recently commenced and this project is anticipated to be advertised for bidding during December. Construction will take place over the summer of 2015. This General Contracting project is being managed via OAKS-CI.

Library Fire Alarm Upgrade
The remaining portions of the Library fire alarm system that were controlled from the old fire alarm control panel were upgraded this summer. Summit Electric's installation of all new fire alarm system devices for this project, designed by EPIC Design Group, was completed August 14. Currently, the contractor is removing the old fire alarm devices and then they will patch and paint areas where the old system was installed. Punch list and project close out items will then follow. This Capitally-funded, General Contracting project is being managed via OAKS-CI.

Medium Voltage Loop 6B
This project completes the process of abandoning the old, unreliable 5kv electrical distribution system in favor of the new and more efficient, higher voltage system. Work involves upgrading cabling and electrical equipment to enable the remaining buildings (Allerton Apartments, Art Building, Child Development Center, DeWeese Health Center, Ice Arena, Harbourt, Heer, Stewart, and VanCampen halls, Student Recreation and Wellness Center, and WKSU Broadcast Center) to accept the 13.2kv distribution voltage. All pre-existing, remaining 5kv cabling and equipment are being removed and a new, 13.2kv capacitor bank is being installed. To date, Lake Erie Electric has converted the Child Development Center, Ice Arena, Stewart Hall, Student Recreation and Wellness Center, WKSU Broadcast Center, Harbourt, Heer and Van Campen Halls, the Art Building and DeWeese Health Center over to the new system. Planned power outages were completed thus far without incident. There will be a few additional, planned power outages this fall and again next spring; the outage dates are dictated by work outside this project and requires coordination with other construction projects. The new, 13.2 kv capacitor bank will be delivered to the site in early October and will be brought online in mid-October. The power factor correcting capacitors will enable for even further energy efficiencies within the electrical distribution system. Work on this project is anticipated to continue through March 2015. This General Contracting project is being managed via OAKS-CI.

Multiple Science Buildings Renovations and Addition
An Integrated Sciences Building will be built to increase academic and research spaces. The 93,000 SF Cunningham Hall, built in 1968, which provides space for the Department of Biological Sciences, will be renovated. Cunningham Hall also includes an addition that was completed in 2001; work in this addition is anticipated to be modest and limited to systems that interface with the original building, such as building automation, security and fire alarms and re-commissioning of the HVAC system. Exterior envelope improvements will be made to Smith Hall (circa 1968) which provides space for the Department of Physics. Renovations of these buildings are being treated as a single project to provide a cohesive approach to science instruction and research space in these areas. This project addresses deferred maintenance needs, focusing on replacement of aging and failing infrastructure and systems. All three buildings and programs will need to continue to operate portions of the buildings during construction. Sharing of temporary facilities in all three areas will be part of an overall sequencing plan for the construction period. Ayers/Saint/Gross, Incorporated, the Architect of Record, is designing and providing project management for all phases of the project. The Mechanical/Electrical/Plumbing engineering firm, Prater Engineering, is under contract with the Architect of Record. Turner Construction Company is serving as Construction Manager at Risk. In addition, separate consultants are under contract to assist Kent State on this project: The Ruhlin Company is serving as the Major Construction Program Manager, Karpinski Engineering, Inc. is the Commissioning Agent, and Doty & Miller Architects & Planners, Inc. is the LEED Process Consultant. This project will be registered with the USGBC for minimum Silver LEED certification. The Program of Requirements is completed; the design team is working on the Design Development phase, while the Construction Manager's work is underway with renovations in Smith Hall and central HVAC replacements in Williams Hall. This Construction Manager at Risk project is being managed via OAKS-CI.

New Building for the College of Applied Engineering, Sustainability and Technology
In support of the recently redefined and renamed College of Applied Engineering, Sustainability and Technology, Kent State University is building a new facility reflecting the level of sophistication envisioned for the college. The new facility will house classrooms, labs and administrative and faculty offices. In addition, a portion of the building will be planned as shell space for future expansion as additional funding becomes available. The research activities of the college will be located in another building on campus. This project will be registered with the USGBC for minimum Silver LEED certification. Bostwick Design Partnership is serving as the Architect of Record; Hammond Construction, Inc. is serving as Construction Manager at Risk. In addition, separate consultants are under contract to assist Kent State on this project: The Ruhlin Company is serving as the Major Construction Program Manager, Doty & Miller Architects & Planners, Inc. is the LEED Process Consultant, and Four Seasons Environmental, Inc. is the Commissioning Agent. Currently, masonry work is nearing completion, windows are being installed, site work is commencing, and finishes are being applied to the lower level and second floor. This Construction Manager at Risk project is being managed via OAKS-CI.

New Facility for the College of Architecture and Environmental Design
The College of Architecture and Environmental Design (CAED) is one of Kent State University’s signature programs. Presently, the program is fractionalized with classroom, studios and faculty offices scattered across the campus in three separate structures that do not reflect the caliber of the program. Taylor Hall is the base of CAED's operations and its location within the May Fourth Historic District makes it impossible to modify the existing building in a constructive way; therefore, the university has set the construction of a new building for the program as a facility improvement priority. The proposed building is programmed at approximately 120,000 SF and will include studios, classrooms, administrative offices and various shop and research spaces. The new building will be located on the Esplanade extension, the path between South Lincoln Street and Haymaker Parkway to connect the Kent Campus with downtown Kent. The connection of the building to its surrounding site will be an important part of the design and the project will include all sidewalks, parking lots, landscaping and utility extensions to the site and building. The university has identified three primary drivers of project: the building must be architecturally significant and representative of the stature of the CAED program; the building must be a model of sustainable design and energy performance; and the building must be affordable while accommodating all of the programmatic needs of the college. Richard L. Bowen + Associates, Inc., in collaboration with Weiss/Manfredi, is serving as the Architect of Record for this project. Gilbane Building Company is serving as the Construction Manager at Risk. In addition, separate consultants are under contract to assist Kent State on this project: The Ruhlin Company is serving as the Major Construction Program Manager, Doty & Miller Architects & Planners, Inc. is the LEED Process Consultant, and Four Seasons Environmental, Inc. is the Commissioning Agent. This project will be registered with the USGBC for minimum Silver LEED certification, but is being designed to a LEED Platinum target. Maximizing energy conservation is a critical component of the design goals to comply with House bill 251. The design team is working on the Construction Documentation phase. New Kent State Architecture Building Generates Excitement in the Architecture Profession. This Construction Manager at Risk project is being managed via OAKS-CI.

Olson Center Rehabilitation for Undergraduate Studies
Olson Center, located along the University Esplanade and adjacent to the Memorial Athletic and Convocation Center, was constructed in 1961 as a dining facility, but was converted to offices in the early 1980s. Building renovations will address the growing list of deferred maintenance issues, but more importantly, will enhance the building facade facing this highly-visited section of the campus. The Department of Undergraduate Studies was located in the Olson Center; the Undergraduate Studies Center for Excellence tutoring and other operations are located in the Schwartz Center and the Library. Undergraduate Studies is responsible for assisting undecided students with degree and career planning; assessing the basic skills of all entering freshman students; providing tutoring services that promote student learning; and providing support tools and resources for low-income, first generation and precollege students. At 28,000 SF, the former kitchen and dining hall areas that recently housed Undergraduate Studies and two departments from the School of Art is being transformed into a modern, student-focused tutoring and exploratory advising center. With its prime location in the center of campus, students could easily access tools to help them achieve success at Kent State University, including group tutoring, walk-in tutoring, online tutoring and scheduled tutoring. The Art programs that were located on the north side of the building are being permanently relocated into the new Art Complex once it is completed. Domokur Architects designed this project; it will be registered with the USGBC for minimum Silver LEED certification. Maximizing energy conservation is a critical component of the design goals to comply with House Bill 251. Separate consultants are under contract to assist Kent State on this project: The Ruhlin Company is serving as the Major Construction Program Manager, Doty & Miller Architects & Planners, Inc. is the LEED Process Consultant, and Four Seasons Environmental, Inc. is the Commissioning Agent. Dunlop & Johnston's on-site construction must be fully completed no later than January 25, 2015. Within the renovation space, the new roof installation was completed in early August before students returned for Fall Semester. Stud walls and drywall are being installed. Foundations and the floor slab are poured for the new addition and steel erection is underway. This General Contracting project is being managed via OAKS-CI.

Renovations and Additions for the School of Art
The School of Art currently occupies seven different buildings on the Kent Campus: the Art Building, Art Annex, Van Deusen Hall, Schwartz Center, Ceramics Building, Olson and Terrace halls. The intent of this project is to consolidate the school into two buildings and provide renovated and new spaces for their programs. The Art Annex is the university's former central heating plant in which a two-phase renovation was planned to house several art programs. Phase one was completed in 2007 and this project will complete the second phase of renovations to provide approximately 32,000 SF. Recommendations to renovate Van Deusen Hall in lieu of the Art Building were approved, enabling the buildings to be linked together by the addition, thus creating space for the entire School of Art to be housed under one roof. Van Deusen needs significant renovations to accommodate the program space; the old Heating Plant section of the Art Annex is being partially demolished and rebuilt. In general, the project provides new MEP infrastructure, interior finishes, and envelope repairs/replacement. This project will be registered with the USGBC for minimum Silver LEED certification. Payto Architects, Inc., the Architect of Record, completed a study with several different renovation scenarios. Ozanne Construction Company served as Construction Management at Risk for Bid Events 1A and 1B, and concluded their work in March. The Ruhlin Company is serving as the Major Construction Program Manager, Doty & Miller Architects & Planners, Inc. is the LEED Process Consultant, and Four Seasons Environmental, Inc. is the Commissioning Agent. Portions of the buildings are remaining occupied during the renovations. Two early construction packages commenced last spring to relocate existing utilities and perform abatement and demolition in the Art Annex and former Heating Plant. Utility work commenced last May and was completed in August. Demolition and abatement work began last September and continued through March. The Knoch Corporation's on-site work to relocate the Graduate Painting and Drawing Studios from Olson Center to the Art Building was completed by mid-May. Multiple-Prime Contracts for site and structural work for the addition in between the Art Annex and Van Deusen Hall were bid by the A/E. Bid Event 02 work is progressing with Precision Engineering & Contracting, 21st Century Concrete Construction, Inc., and Lake Building Products on-site. Baumann Enterprises, 21st Century Concrete Construction, Thomarios, S. A. Comunale Co., Summit Electric, Echo 24, Johnson Controls, and ABC Piping Co. are involved in the construction process with major demolition, foundations and steel erection underway. This Bid Event 03 work is scheduled to be completed on December 28, 2015. Foundations of Excellence: The Center for the Visual Arts Complex, Featured Video, April 7, 2014. This multiple-phased project is being managed via OAKS-CI.

Rockwell Hall Museum Fire Suppression System Replacement
Rockwell Hall was built in 1928 as the university’s first main library. After the current main library opened in 1970, Rockwell Hall then served as an administrative building until it was renovated and repurposed as the Kent State Fashion Museum in 1990. The Fashion Museum houses rare and historically significant garments and artifacts; these collections are currently protected from fire by a carbon dioxide (CO2) fire suppression system that was installed at the time of the renovation. The system has reached the end of its useful life and does not provide adequate protection of the collections. This project will remove the existing CO2 system and replace it with a dry-pipe, pre-action system on all floors and expanded basement level of Rockwell Hall. This Design-Build project is being managed via OAKS-CI.

Salem Classroom Building Partial Roof Replacement
Kent State University at Salem is replacing two large areas of roof at the Classroom Building with a new, single-ply, 20-year warrantied membrane system. The project was designed in-house by the Office of the University Architect. The construction bids that were opened on October 14th were rejected; the project is being re-bid and the new bid opening date is scheduled for October 28. This General Contracting project is being managed via OAKS-CI.

Salem Classroom Building Second Floor Build-Out
This project will complete the build-out of the Salem Campus' Classroom Building second floor Science Wing and will include a biology lab and prep room; a chemistry lab, prep room, instrumentation room, and storage room; two general classrooms; a general storage room; and two student restrooms. Stitle Construction Corporation commenced construction on August 25 and their work continues through January 6, 2015 for this project that was designed by Hasenstab Architects. New walls have been completely framed and installations of mechanical and electrical systems are underway. Installation of gypsum board on the walls will commence during the week of September 22, with finishes and equipment installation soon to follow. This Capitally-funded, General Contracting project is being managed via OAKS-CI.

Stark Library HVAC and Ceiling Replacement
The second phase of this multiple-phased project, involves HVAC upgrades and interior renovations to Stark's Library Building. The Library Building, built in 1976, houses the Library, offices, classrooms and supports spaces. This second phase involves replacement of the custom Moduline air terminal units, associated ductwork and diffusers in preparation for a new VAV terminal unit with hydronic reheat coils. A boiler reheat system with distribution with limited piping throughout the building is planned to expand the system. This project was designed for future phases including installation of a new ceiling, lighting and sprinkler system. The design is based upon a standard ceiling grid layout; this new design will move away from the custom tile the campus has today. To enhance energy reduction, the design also explores the replacement of lighting systems with new LED fixtures. The enhanced design will allow the HVAC system to account for the sprinkler system, ceiling and lighting so that the mechanical system will not have to be modified in the future. Peters Tschantz & Associates, Inc. designed this multiple-phase project. The Standard Plumbing and Heating Company is nearing completion of the mechanical system upgrades under this phase. Elevator work associated with the fire alarm upgrade will be completed during winter break. This Capitally-funded, General Contracting project is being managed via OAKS-CI.

Stark Maintenance Building Envelope Repairs and Roof Replacement
Stark Campus' Maintenance Building's masonry was in poor condition and in need of repair. The roof was in poor condition with several active leaks and is in need of significant repairs. This project involves masonry repairs, including brick replacements, tuckpointing, replacement of exterior sealants, repairs of exterior doors and railings. The building will be power-washed and water repellant will be applied. The majority of damaged brick and damaged mortar joints should all be removed and replaced by late September. By the end of September, the metal roof, all flashings, gutters and insulation are scheduled to be replaced with a new roofing system with a 30-year warranty. Jeffrey Carr Construction's on-site work, including the installation of overhead doors and painting, is scheduled to be completed by the end of October for this project that was designed by Harris/Day Architects, Inc. This General Contracting project is being managed via OAKS-CI.

Stark Sciences Building
BHDP Architecture assisted the university with designing a new Kent State University at Stark Sciences Building of approximately 41,140 SF and renovating approximately 5,250 SF of the existing Main Hall East Wing. Heapy Engineering is serving as the Commissioning Agent. The new building will support the Science programs and will accommodate science teaching and research laboratories such as biology, physics, and geology, as well as nursing laboratories and classrooms. The building will also include general and computer classrooms, faculty offices and a student cyber lounge. Main Hall East Wing will then be renovated and the existing Biology laboratories and prep/storage areas will be converted to accommodate the Chemistry program. The new building will be located adjacent to the existing Main Hall East Wing with a link at the second floor to connect the new Sciences Building with the renovated science laboratories in the Main Hall East Wing. Site development includes a building receiving area, accessible parking, pedestrian walkways, lighting and landscaping. Jeffrey Carr Construction's work on the new building is scheduled to be completed by the spring of 2015. The new construction work is progressing toward building enclosure by October with the exterior sheathing 75% complete and roofing 25% complete. Mechanical, electrical and plumbing installations are underway within the building interior. Steel has been erected to connect the new addition to the existing East Wing. Renovations to the vacated spaces are scheduled to occur during the spring/summer of 2015. This Capitally-funded, General Contracting project is being managed via OAKS-CI.

Student Memorial Garden
To create a singular location for student memorials, the Student Memorial Garden is being built on the Kent Campus for students to remember and recognize students that have passed away. In August, Hummel Construction Company and W. T. Leone's Tri-Area Electric Company commenced work on this project that was designed by Robert D. Morgan, LLC. Construction of this project is anticipated to be completed by December 1. This Multiple-Prime project is being managed via OAKS-CI.

Tri-Towers Residence Halls Rooms and HVAC Upgrades
Built in 1968, the Tri-Towers complex consists of two ten-story residence halls, one twelve-story residence hall and a central connecting building for dining and student activities. The complex houses approximately 1,400 students and previously received two large-scale, but partial renovations within the last ten years. This project addresses deferred maintenance issues, including aging HVAC infrastructure, building envelope failures, interior room configurations and finishes that were not corrected as part of previous renovations and extending the life of the buildings for another thirty years. Domokur Architects is serving as the Architect of Record to assist with designing and providing project management for all phases of the project. The AOR contracted directly with Scheeser Buckley Mayfield for MEP engineering design. Four Seasons Environmental is under contract with the university to serve as the Commissioning Agent. Gilbane Building Company is serving as Construction Manager at Risk for this project. Construction was scheduled over a two-year time frame, with the majority of work completed while buildings were unoccupied during the summer breaks of 2013 through 2014. Work in Wright Hall was completed the summer of 2013, in time for students moving into the hall. This summer, Koonce and Leebrick halls were completed in time for students moving into the halls. As weather permits, building envelope work continues through the end of September to allow for landscaping work to be completed before winter sets in. This Construction Manager at Risk project is being managed via OAKS-CI.

Tuscarawas University Hall and Attention Center Demolition
Kent State University at Tuscarawas' University Hall and the Attention Center are under consideration by the Tuscarawas County University District Board for abatement and demolition in early 2015. Asbestos abatement analyses were conducted and construction documents have been prepared for the removal of both buildings. This General Contracting project is being managed via OAKS-CI.